Scheduled intervention : Firewall migration (phase 3) Thursday 24th January 2019 23:00:00


Estimated timeframe : 23:00-08:00


Actual timeframe : 23:08-06:35


Objective

Replace the current aging firewall with a modernized architecture

Operations

Impact

Mitigation

06:35 Final configuration & testing finished ; the new firewall is live.

05:59 This is starting to get into shape.

23:08 configuration & testing started