Scheduled intervention : FS4 data migration Saturday 27th March 2021 21:45:00


Estimated timeframe : 21:45-15:00


Actual timeframe : 21:45-17:08


Objective

Migrate FS4 datasets to intermediary storage volumes

Actions

Impact

Mitigation

17:08 final cleanup completed ; migration completed

16:09 starting final cleanup

16:08 completed 'irccloud' synchronization

15:25 started 'irccloud' synchronization

12:55 completed 'Sequencing' synchronization

11:31 completed 'Particle Analysis', 'CT Scans' & 'BD Pathway' synchronization

10:40 started 'Particle Analysis', 'CT Scans' & 'BD Pathway' synchronization

00:30 started 'Particle Analysis', 'CT Scans' & 'BD Pathway' migration

00:25 completed 'Flow Cytometry' synchronization

21:56 started 'irccloud' migration

21:50 started 'Sequencing' synchronization

21:45 started 'Flow Cytometry' synchronization