All systems are operational

Past Incidents

4th March 2020

No incidents reported

3rd March 2020

No incidents reported

2nd March 2020

No incidents reported

1st March 2020

FSVM Backbone Scheduled upgrade : network backbone distribution migration

Estimated timeframe : 14:30-17:30


Actual timeframe : 14:30-20:10


Objective

Migrate distribution switches to new network core

Actions

  • migrate FSVM1 distribution switches
  • prepare iGent distribution stack migration

Impact

  • During the migration, network zones will experience a short interruption.

Mitigation

  • Do not rely on uninterrupted network connectivity
  • Do not initiate long-term network data transfers

29th February 2020

FSVM Core Scheduled upgrade : network backbone core replacement

Estimated timeframe : 14:30-16:30

Actual timeframe : 14:30-16:32


Objective

Replace current core switch stack with new core switch stack

Impact

  • During the migration, all network connectivity will be intermittently interrupted.

Mitigation

  • Do not rely on uninterrupted network connectivity
  • Do not initiate long-term network data transfers

28th February 2020

No incidents reported

27th February 2020

No incidents reported